居家地暖工程施工技巧
Construction techniques of home heating project
1、 施工准备(含清理地面)→安装固定分、集水器→铺设绝热板和边界膨胀带→地暖反射膜→铺设盘管(PEX、PERT、PB等)
:加热盘管铺设的顺序是从远到近逐个环圈铺设,凡是加热盘管穿地面膨胀缝处,一律用膨胀条将地面分隔开来,加热盘管在此处均须加伸缩节,伸缩节为加热盘管专用伸缩节,其接口连接以加热管品种确定。施工中须由土建与安装事先划分好→设置过门伸缩缝(含盖钢丝网)→中间验收(一次水压试验)→回填细石混凝土层→完工验收(二次水压试验
)。(专用温控器最后安装)竣工结束时,绘制图纸,准确标注盘管位置和地温传感器的埋设地点。
1, construction preparation (including cleaning ground) -
Installation of fixed points, water collector, adiabatic plate and
boundary expansion belt, floor heating reflecting film and paving coil
(PEX, PERT, PB, etc.): the order of heating coil laying is to lay from
far to near ring ring. Apart from this, the heating coil units must be
provided with expansion joints. The expansion joint is a special
expansion joint for heating coil units, and the interface connection is
determined by the variety of heating pipes. In the construction, the
construction and installation must be divided in advance - setting up
the expansion joint of the door (including the cover wire mesh) - the
intermediate acceptance (one water pressure test) - backfilling the fine
stone concrete layer and the completion acceptance (the two water
pressure test). (final installation of the special thermostat) at the
end of the completion, draw up the drawings, accurately mark the
location of the coil and the location of the ground temperature sensor.
常规地暖施工层次解剖图
Stratified anatomical map of conventional ground heating construction
2、卫生清理,建筑垃圾及灰尘
2. Sanitary cleaning, construction waste and dust
3、绝热层的铺设:
3. The laying of the adiabatic layer:
铺设绝热层的地面应平整、干燥、无杂物。墙面根部应平、直且无积灰现象。绝热层的铺设应平整,绝热层相互间的接缝应严密。直接与土壤接触的或有潮气侵入的地面,在铺放绝热层之前应先铺一层防潮层。
The ground should be flat, dry and free of sundries. The root of
the wall should be flat, straight and without ash accumulation. The
insulation layer should be laid flat and the joints between the
insulation layers should be tight. A soil moisture barrier should be
laid on the ground that is directly in contact with the soil or with
moisture intrusion.
聚苯乙烯泡沫塑料板绝热层厚度(mm) 楼层之间楼板上的绝热层 20 与土壤或室外空气相邻的地板上的绝热层 40
The insulation thickness of polystyrene foam board (mm), the
insulation layer between floors, the insulation layer 20 on the floor
adjacent to the soil or outdoor air, and the insulation layer 40.
重视边角隔热层的设置和就位
Attach importance to the setting and placement of the side angle heat insulation layer
伸缩缝的设置:
The setting of the expansion joint:
1. 在与内外墙、柱及过门等交接处应敷设不间断的伸缩缝,伸缩缝连接处应采用搭接方式,搭接宽度不小于10mm;伸缩缝与墙、柱应有可靠的固定方式,与地面绝热层连接应紧密,伸缩缝宽度不宜小于20mm。伸缩缝宜采用聚苯乙烯或高发泡聚乙烯泡沫塑料。
1. in the junction with internal and external walls, columns and
doors and other joints should be laid uninterrupted expansion joints,
expansion joints should be connected to the joint way, lap width is not
less than 10mm; expansion joints and walls, columns should be reliable
fixed mode, connected to the ground floor insulation, expansion joint
width should not be less than 20mm. Expansion joints should be made of
polystyrene or high foamed polyethylene foam.
2. 当地面面积超过30㎡或边长超过6m时,应按不大于6m间距设置伸缩缝,伸缩缝宽度不小于8mm(一般工地我们做10mm)。伸缩缝宜采用高发泡聚乙烯泡沫塑料或内满填弹性膨胀膏。
2. when the surface area is more than 30 or more than 6m, the
expansion joint should be set at the distance of no more than 6m, and
the width of the expansion joint is not less than 8mm (general site we
do 10mm). Expansion joints should be made of high foamed polyethylene
foam or filled with elastic expansion paste.
3. 伸缩缝应从绝热层的上边缘到填充层的上边缘整个截面上隔开。
3. the expansion joint should be separated from the upper edge of
the insulation layer to the upper edge of the filling layer and the
entire section.
发泡水泥隔热层的验收
Acceptance of foamed cement insulation layer
每100立方作为一个检验批
Every 100 cubic meters is used as a test batch
表面质量检测
Surface quality detection
密度测定:按GB/T11970中的方法
Density measurement: according to the method in GB/T11970
抗压强度测定,同上
Determination of compressive strength, same as above
厚度测量,随机抽检
Thickness measurement, random sampling
4、铺反射膜
4. Paving reflection film
5、卫生间施工 :
5. Toilet construction:
卫生间应做两层隔离层,作法可参见《低温热水地面辐射供暖技术规程》附录 A。
The toilet should be made of two layers of isolation layer. The
method can be seen in Appendix A of the technical specification for low
temperature hot water floor radiant heating.
卫生间过门处应设置止水墙,在止水墙内侧应配合土建专业作防水,以防止卫生间积水渗入绝热层,并沿绝热层渗入其它区域。加热管穿止水墙处应保定平面设计培训 收费岛模具 挡土墙模具 防撞墙模具 防撞墙模具 防撞护栏模具 大棚遮阳网 遮阴网设防水套管,防水套管两端应加密封。
The water stop wall should be set at the door of the toilet. In the
inner wall of the water stop wall, the waterproofing should be combined
with the civil engineering specialty to prevent the water from seeper
into the insulation layer and infiltrate into other areas along the
adiabatic layer. Waterproofing sleeves should be installed at the wall
of the heating pipe through the watertight wall, and the ends of the
waterproof bushing should be sealed.
做完防水闭水试验并经过验收。
Finish the water proof and closed water test and pass the acceptance |